Project
Initially invited by the Academy Trust to undertake a Planned Maintenance Survey, permitted intrusive inspections necessitated the need for a Condition Survey which identified a number of issues including rotten timber frame, damaged timber cladding, flat roof issues, poor lighting and issues with fire door access points.
After the report had been sent to the client there was a direct enquiry from the DfE about costs for remedying what were, effectively, dilapidations inherited from the local authority who had previously run the infant & nursery school.
BTG Eddisons was invited to specify and conduct a schedule of works and tender for the management of the project for the Academy Trust in liaison with its senior management team and oversight from the DfE. Costs were negotiated in acknowledging the level to which central departmental public funds were available.
With the works project contract, which included drawings, awarded to Eddisons, competitive tendering saw locally based firm Harper Interiors appointed as the contractor for the construction and built elements and new interior fitout, reporting to BTG Eddisons as the overall project manager and QS.
Ahead of starting on site, the scope of BTG Eddisons’ work included CDM 2015 and Building Safety Act advice as well as local building control pre-approvals.
Approach
While the construction works on site on the main timber-framed building and portable cabin commenced during the school summer holiday period of 2025, the extent of the work was always going to see the project carry through to the Autumn term, with a scheduled finish just in time for the end of the year.
The focus was on the nursery school first to strip out and complete its refurbishment during the 6 weeks of holiday ready for the new intake and then the infant school could decant into the nursery space to allow the infant block to be refurbished once term had started.
The view was to upgrade the portable cabin – which was used for storage and, initially, scheduled for demolition as part of the project – in order for it to be used as a temporary teaching space, in which to decant the classes as the progress of the works necessitated.
However, after the upgrade of the portable cabin for this temporary use, the feeling among the client’s teaching staff was that it was, in the long term, such a high-quality space that it would be retained and provide much-needed two additional teaching areas even after the project had completed.
Features of the refurbishment include external recladding, new flat roofing, new ceilings, lighting and emergency lighting, fire doors and fire alarm systems work, electrical safety work, heating, electrical safety work, internal finishes and complete refurbishment of the toilets.
Result
With handover to the client in January 2026 post-snagging, this project, which involved co-ordination and co-operation between so many parties, has transformed the infant and nursery school building to provide a fresh, welcoming and vibrant teaching & learning environment to be enjoyed by the staff and the children.
“As a Trust we worked closely with BTG Eddisons and, in particular, Nick Galloway to redesign and renew the fabric of Broadmeadow Infant School building.
From start to finish Nick handled the project superbly and, as a result of his meticulous approach, the project was a complete success and completed ahead of time. I, personally, cannot rate Nick highly enough – he is superb.”
Steve Taylor, CEO, Robin Hood Multi Academy Trust
Why Should I Choose Eddisons Education for Estate Modernisation Projects?
We provide strategic estate planning, refurbishment and modernisation services for education providers across the UK.
Our team understands the challenges of delivering improvements within live learning environments, often across diverse and ageing property portfolios. Here are some reasons to consider us for your next project:
- We have over 180 years of experience
- Our teams have a proven track record
- Past clients rate us highly
- Our specialists are RICS-certified for your peace of mind
- We deliver consistent specification, procurement and contract administration aligned with long-term property strategies
Modernise Your Learning Estate with Confidence with BTG Eddisons
If your organisation is seeking to rationalise, refurbish or future-proof its estate, our specialists can support you from initial feasibility through to project delivery. We work collaboratively with stakeholders to ensure safe, compliant and value-driven outcomes that enhance user experience while maintaining operational continuity.
Please call 0808 175 9289 or complete the form below to arrange a free consultation and discuss how we can support your estate modernisation plans.
Latest news and insights
View our latest news along with insights from our expert team of chartered surveyors on all things education estates.